We always get the job done being a tangible workforce making sure that we can easily give you the very best quality as well as finest selling price for Oil Fueled Boiler, biomass boiler induced draft fan, Hot Water Boilers, At our firm with good quality initially as our motto, we manufacture merchandise that are entirely made in Japan, from materials procurement to processing. This enables them for being used with confident peace of mind.
Boiler Accessory Supplier - Installation & Technology Service – Double Rings Detail:

Installation Procedure

Step 1. Slag Extruder put into Foundation|
Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair.
Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue.
Step 4. Connect Economizer ( Up Parts) and Gas Flue.
Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak.
Step 6. Lift Dust Cleaner to Foundation.
Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer .
Step 8. Lift I.D Fan to Foundation
Step 9. Connect and fix the Gas Flue between Dust Cleaner and I.D Fan .
Step 10. Lift and Install Chimney , Connect I.D Fan with Chimney.
Step 11. Install F.D Fan
Step 12. Install Coal Feeder
Step 13. Install Reducer
Step 14. Install Valve&Gauge in Boiler Body
Install Valve&Gauge of Economizer
Step 15. Install Steam Distribution Cylinder,connect Main Steam Pipe and Valve&Gauge.
Customer arrange Steam Pipe Route according to the real situation in their factory.
Step 16. Install Water Pump and Valve&Gauge
Customer arrange Water Pipe Route according to the real situation in their factory.
Vertical Style Stainless Steel Water Pump need Vertically Installation.
Step 17. Install the Light,Motor Electric Wire and Electric Control Cabinet
Customer arrange Electric Wire Route according to the real situation in their factory.
Step 18. Install Water Treatment
All Boiler Installation Finish
Steam Boiler Equipment Layout
Note: This Procedure was recommended by Double Rings. Real Operation is according to local situation and Manual.   Photos in the paper is just to display.Real Equipments are subject to actual receipt cargo.

Service after Sale

Service after Sale:
Warrant Time One Year for Whole Boiler without mistake operation after shipment.
Technology Service For life.Customer has any questions about the boiler, our engineers will serve and supply the Technology Service immediately.
Guidance Installation After finish the foundation and boiler arrived in the customer’s factory,two engineers will go to customer’s factory to guidance installation with local workers .
Commissioning After installed, the boiler will be commissioning and training for 2days.
Charge The buyer should provide air tickets with round trip, accommodation, food and local communication and transportation for the engineers, plus the subsidy  for each engineer.

 


Product detail pictures:


Related Product Guide:
Boiler Structure

We insist on offering high-quality production with great enterprise concept, honest product sales and also the finest and fast service. it will bring you not only the superior quality solution and huge profit, but the most significant should be to occupy the endless market for Boiler Accessory Supplier - Installation & Technology Service – Double Rings , The product will supply to all over the world, such as: Gabon, Kenya, The Swiss, Our staffs are adhering to the "Integrity-based and Interactive Development" spirit, and the tenet of "First-class Quality with Excellent Service". According to the needs of every customer, we provide customized & personalized services to help customers achieve their goals successfully. Welcome clients from home and abroad to call and inquire!
The company can keep up with the changes in this industry market, product updates fast and the price is cheap, this is our second cooperation, it's good.
5 Stars By Tyler Larson from Greek - 2017.08.16 13:39
Adhering to the business principle of mutual benefits, we have a happy and successful transaction, we think we will be the best business partner.
5 Stars By Odelia from Florida - 2018.09.23 18:44
Write your message here and send it to us

Related products

  • Wholesale Discount Fire Tube Boiler - Steam&Hot Water Pipe – Double Rings

    Wholesale Discount Fire Tube Boiler - Steam&am...

    Products Description Structure Steel pipe– insulation layer–steel jacket pipe Steel pipe process 1. Seamless, 2. Spiral steel pipe( SAW) 3. Straight steel pipe(ERW) Insulation layer of external sliding type Fiberglass wool or rock wool Insulation layer of internal sliding type 1. Calcium silicate insulation material 2. Polyurethane insulation material Application 1. Steam 2. Hot oil 3. Hot material Specification DN57-1020mm(1 inch-64 inch) Medium temperature...

  • China Lpg Hot Water Boiler - SZS Gas Oil PLG Boiler – Double Rings

    China Lpg Hot Water Boiler - SZS Gas Oil PLG B...

    Introduction : SZS series boiler body is longitudinal 2-drum, D-type chamber combustion strueture. The furnace is on right side and the convection bank tube is on left side. The body is fixed on the body chassis by flexible supports in the middle and two ends of the lower drum,can secure to let the whole boiler body to expand sideways. Surround furnace there are narrow space membrane cooling tube wall. It is totally sealed and separated between the membrane wall on furnace left side and the c...

  • China Biomass Boiler Device - Single Drum Steam Boiler – Double Rings

    China Biomass Boiler Device - Single Drum Stea...

    Introduction : Single Drum Chain Grate Coal fired boiler is horizontal three-back water fire pipe composite boiler. Fix fire tube in drum and the light pipe water wall is fixed on the right and left sides of the furnace. With light chain grate stoker for mechanical feeding and by the draft fan and blower for mechanical ventilation, realize mechanical taphole by scraper slag remover. The hopper of fuel drops to grate bar, then enter furnace for burning, by the ashes room above the back arch, t...

  • Short Lead Time for Water Tube Boilers - Autoclave and Boiler – Double Rings

    Short Lead Time for Water Tube Boilers - Autoc...

    Autoclave-Popular used in ACC Plant,Flyash Plant,Building Material etc.. Autoclave Feature 1, the first domestic production of autoclave professional factory. 2, assembly line production, welding all the automation, quality and stability. 3, all the pressure components 100% X-ray film detection, advanced detection methods. 4, the product as a whole factory, advanced and reasonable structure, short installation period, the investment cost is low. 5, fully furnished, by manual or com...

  • Competitive Price for Pressure For Boiler - Boiler Steam Distribution Cylinder – Double Rings

    Competitive Price for Pressure For Boiler - Bo...

    Used in Boiler Introduction The sub-cylinder is the main supporting equipment of the boiler. It is used to distribute the steam generated during the operation of the boiler to various pipelines. The sub-cylinder is a pressure-bearing equipment and belongs to a pressure vessel. Its pressure-bearing capacity and capacity should correspond to the supporting boiler . Main pressure components The main pressure components of the sub-cylinder are: head, shell material, etc. Usage The sub-cylin...

  • Manufactur standard Coal Boiler - Well-designed Biomass Pellet Boiler - Coal Boiler Biomass Boiler Reducer – Double Rings – Double Rings

    Manufactur standard Coal Boiler - Well-designe...

    Reducer used in DR Boiler • The main parts adopt high quality carbon structural refined steel.With high strength, high transmission efficiency and reliable operation, long service life, etc. • Respectively using multilevel, stepless frequency conversion speed regulating mode. User can reasonably match speed reducer according to the different operation condition of boiler.With the features of easy operation, energy saving, etc • With characteristics of large transmission torque and speed...