In the past few years, our business absorbed and digested advanced technologies both equally at home and abroad. In the meantime, our company staffs a group of experts devoted to your advancement of chinese economizer, coke fired boiler, Coal Fired Boilers, We sincerely welcome all guests to set up business relationships with us on the basis of mutual benefits. Please contact us now. You will get our professional reply within 8 hours.
China Steam Boiler Electric Manufacturers - Installation & Technology Service – Double Rings Detail:

Installation Procedure

Step 1. Slag Extruder put into Foundation|
Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair.
Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue.
Step 4. Connect Economizer ( Up Parts) and Gas Flue.
Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak.
Step 6. Lift Dust Cleaner to Foundation.
Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer .
Step 8. Lift I.D Fan to Foundation
Step 9. Connect and fix the Gas Flue between Dust Cleaner and I.D Fan .
Step 10. Lift and Install Chimney , Connect I.D Fan with Chimney.
Step 11. Install F.D Fan
Step 12. Install Coal Feeder
Step 13. Install Reducer
Step 14. Install Valve&Gauge in Boiler Body
Install Valve&Gauge of Economizer
Step 15. Install Steam Distribution Cylinder,connect Main Steam Pipe and Valve&Gauge.
Customer arrange Steam Pipe Route according to the real situation in their factory.
Step 16. Install Water Pump and Valve&Gauge
Customer arrange Water Pipe Route according to the real situation in their factory.
Vertical Style Stainless Steel Water Pump need Vertically Installation.
Step 17. Install the Light,Motor Electric Wire and Electric Control Cabinet
Customer arrange Electric Wire Route according to the real situation in their factory.
Step 18. Install Water Treatment
All Boiler Installation Finish
Steam Boiler Equipment Layout
Note: This Procedure was recommended by Double Rings. Real Operation is according to local situation and Manual.   Photos in the paper is just to display.Real Equipments are subject to actual receipt cargo.

Service after Sale

Service after Sale:
Warrant Time One Year for Whole Boiler without mistake operation after shipment.
Technology Service For life.Customer has any questions about the boiler, our engineers will serve and supply the Technology Service immediately.
Guidance Installation After finish the foundation and boiler arrived in the customer’s factory,two engineers will go to customer’s factory to guidance installation with local workers .
Commissioning After installed, the boiler will be commissioning and training for 2days.
Charge The buyer should provide air tickets with round trip, accommodation, food and local communication and transportation for the engineers, plus the subsidy  for each engineer.

 


Product detail pictures:


Related Product Guide:
Boiler Structure

Being supported by an advanced and specialist IT team, we could give technical support on pre-sales & after-sales services for China Steam Boiler Electric Manufacturers - Installation & Technology Service – Double Rings , The product will supply to all over the world, such as: Florida, Milan, Bolivia, With its rich manufacturing experience, high-quality products, and perfect after-sale service, the company has gained good reputation and has become one of the famous enterprise specialized in manufacturing series.We sincerely hope to establish business relation with you and pursue mutual benefit.
High production efficiency and good product quality, fast delivery and completed after-sale protection, a right choice, a best choice.
5 Stars By Juliet from Macedonia - 2017.05.02 11:33
This supplier stick to the principle of "Quality first, Honesty as base", it is absolutely to be trust.
5 Stars By Mamie from UK - 2018.12.10 19:03
Write your message here and send it to us

Related products

  • Short Lead Time for Biomass Boiler Cost - Coal Boiler Chain Grate – Double Rings

    Short Lead Time for Biomass Boiler Cost - Coal...

    More phtos The patent material  RTSiCr,RQTSi4Mo which is our company’s unique material. High temperature resistance, Special process, longer service life.   Travelling type grate stoker Spare Parts—Grate Bar The structure is simple, the metal consumption is small, the ventilation section ratio is large, and the strength and performance requirements of the driving shaft, the driven shaft and the grate are high.

  • Best Price for China Coal Boiler - Coal Boiler Biomass Boiler Water Flim Dust Cleaner – Double Rings

    Best Price for China Coal Boiler - Coal Boiler...

    Quality Control 1 Strength Calculation Report for Applied Materials after Inspection Machine inspected. 2 100%NDT(non-destructive inspection) report of steel plate,tube and welding rod; 3 100% X-ray inspection report (welding seam):to ensure the quality of the entire boiler; 4 Hydraulic test report:ensure the standard working pressure and safety; 5 Third-party inspection report:by Special Equipment Safety Supervision Inspection Institute of Jiang Su Province 6 Manufacturer Produc...

  • China Coal Boiler - heat recovery boiler – Double Rings

    China Coal Boiler - heat recovery boiler ̵...

    Introduction: Main Performance Parameter List Steam Pressure 1.0~2.5 Mpa Inlet Temperature 250℃ Saturation Temperature 179℃ Heating Water:Inlet Temperature 90℃; Outlet Temperature 140℃

  • Boiler Economizer Manufacturers - Installation & Technology Service – Double Rings

    Boiler Economizer Manufacturers - Installation...

    Installation Procedure Step 1. Slag Extruder put into Foundation| Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair. Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue. Step 4. Connect Economizer ( Up Parts) and Gas Flue. Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak. Step 6. Lift Dust Cleaner to Foundation. Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer . Step 8. Lift I.D Fan to Foundation Step...

  • PriceList for Hot Water Pipe - Coal Boiler Biomass Boiler Chimney – Double Rings

    PriceList for Hot Water Pipe - Coal Boiler Bio...

    Used in Boiler The height of a chimney affects its ability to deliver flue gas to the external environment through the chimney effect. In addition, the diffusion of pollutants using chimneys at high altitudes can reduce the impact on the surrounding environment. A chimney high enough to allow the chemicals in the air to partially or completely neutralize themselves before reaching the ground level, in the case of chemical erosion. Dispersion of pollutants over a larger area reduces their conc...

  • Discount wholesale Boiler Work - Boiler Electric Control – Double Rings

    Discount wholesale Boiler Work - Boiler Electr...

    More Photos Electric Control Container Overview 2-4T 6T 10T 15T 20T 25T Sheet 1: 2t steam boiler electrical instrument control system configuration (common configuration 1.25Mpa) Features name Specification unit Qty Brand Electrical control           Induced draft fan control 11KW  Star Delta Start  set  1  Zhengtai Blower control  3KW  Direct start  set  1  Grate control  0.55KW  Direct start  set  1  Coal machine control 1.1KW  Direct start  set  1  Slag machine control ...