To consistently enhance the management method by virtue of the rule of "sincerely, fantastic religion and top quality are the base of business development", we extensively absorb the essence of associated goods internationally, and constantly acquire new merchandise to satisfy the needs of shoppers for chinese boiler economizer, pellet steam boiler, Bosch Boiler, We would like to take this opportunity to establish long-term business relationships with clients from all over the world.
Chinese wholesale Industrial Steam Boilers - Installation & Technology Service – Double Rings Detail:

Installation Procedure

Step 1. Slag Extruder put into Foundation|
Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair.
Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue.
Step 4. Connect Economizer ( Up Parts) and Gas Flue.
Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak.
Step 6. Lift Dust Cleaner to Foundation.
Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer .
Step 8. Lift I.D Fan to Foundation
Step 9. Connect and fix the Gas Flue between Dust Cleaner and I.D Fan .
Step 10. Lift and Install Chimney , Connect I.D Fan with Chimney.
Step 11. Install F.D Fan
Step 12. Install Coal Feeder
Step 13. Install Reducer
Step 14. Install Valve&Gauge in Boiler Body
Install Valve&Gauge of Economizer
Step 15. Install Steam Distribution Cylinder,connect Main Steam Pipe and Valve&Gauge.
Customer arrange Steam Pipe Route according to the real situation in their factory.
Step 16. Install Water Pump and Valve&Gauge
Customer arrange Water Pipe Route according to the real situation in their factory.
Vertical Style Stainless Steel Water Pump need Vertically Installation.
Step 17. Install the Light,Motor Electric Wire and Electric Control Cabinet
Customer arrange Electric Wire Route according to the real situation in their factory.
Step 18. Install Water Treatment
All Boiler Installation Finish
Steam Boiler Equipment Layout
Note: This Procedure was recommended by Double Rings. Real Operation is according to local situation and Manual.   Photos in the paper is just to display.Real Equipments are subject to actual receipt cargo.

Service after Sale

Service after Sale:
Warrant Time One Year for Whole Boiler without mistake operation after shipment.
Technology Service For life.Customer has any questions about the boiler, our engineers will serve and supply the Technology Service immediately.
Guidance Installation After finish the foundation and boiler arrived in the customer’s factory,two engineers will go to customer’s factory to guidance installation with local workers .
Commissioning After installed, the boiler will be commissioning and training for 2days.
Charge The buyer should provide air tickets with round trip, accommodation, food and local communication and transportation for the engineers, plus the subsidy  for each engineer.

 


Product detail pictures:

Chinese wholesale Industrial Steam Boilers - Installation & Technology Service – Double Rings detail pictures

Chinese wholesale Industrial Steam Boilers - Installation & Technology Service – Double Rings detail pictures


Related Product Guide:
Boiler Structure

We believe that long term partnership is a result of high quality, value added service, rich experience and personal contact for Chinese wholesale Industrial Steam Boilers - Installation & Technology Service – Double Rings , The product will supply to all over the world, such as: Honduras, Namibia, Czech Republic, We supply skilled service, prompt reply, timely delivery, excellent quality and best price to our customers. Satisfaction and good credit to every customer is our priority. We focus on every detail of order processing for customers till they have received safe and sound items with good logistics service and economical cost. Depending on this, our products and solutions are sold very well in the countries in Africa, the Mid-East and Southeast Asia. Adhering to the business philosophy of ??customer first, forge ahead', we sincerely welcome clients from at home and abroad to cooperate with us.
  • As an international trading company, we have numerous partners, but about your company, I just want to say, you are really good, wide range, good quality, reasonable prices, warm and thoughtful service, advanced technology and equipment and workers have professional training, feedback and product update is timely, in short, this is a very pleasant cooperation, and we look forward to the next cooperation!
    5 Stars By Charlotte from Finland - 2017.12.09 14:01
    The factory workers have a good team spirit, so we received high quality products fast, in addition, the price is also appropriate, this is a very good and reliable Chinese manufacturers.
    5 Stars By James Brown from Hongkong - 2018.05.15 10:52
    Write your message here and send it to us

    Related products

    • Biomass Pellet Boiler - Pressure Vessel – Double Rings

      Biomass Pellet Boiler - Pressure Vessel –...

      Introduction: Pressure vessel equipment plays an important role in the petrochemical industry, the energy industry, scientific research and military sectors etc. Pressure vessel container body consist of cylinder, sealing head, flange, sealing elements, open pore and connected pipe, bearing. In addition, also equipped with safety devices, meter and safety internals for protection purpose . Pressure Vessel Main Performance Parameter List Steam Pressure1.0Mpa Inlet Temperature 250℃ S...

    • Factory directly supply Heat Boilers - Coal Boiler Biomass Boiler Slag Remover – Double Rings

      Factory directly supply Heat Boilers - Coal Bo...

      Slag Remover used in Coal Boiler Introduction The Slag Remover is a kind of boiler slag tapping equipment. The carbon slag produced after the coal is burned in the boiler is pushed to the slag storage pit by the grate, and is dragged out of the furnace by the slag machine to clear the slag accumulation.  Technology The high-temperature slag discharged from the furnace is first crushed into small pieces by a pair-roller slag breaker, which is convenient for cooling and transportation; th...

    • Gas Steam Boiler Factories - Boiler Steam Distribution Cylinder – Double Rings

      Gas Steam Boiler Factories - Boiler Steam Dist...

      Used in Boiler Introduction The sub-cylinder is the main supporting equipment of the boiler. It is used to distribute the steam generated during the operation of the boiler to various pipelines. The sub-cylinder is a pressure-bearing equipment and belongs to a pressure vessel. Its pressure-bearing capacity and capacity should correspond to the supporting boiler . Main pressure components The main pressure components of the sub-cylinder are: head, shell material, etc. Usage The sub-cylin...

    • 18 Years Factory Oil Fired Combi Boiler - Biomass Steam Boiler – Double Rings

      18 Years Factory Oil Fired Combi Boiler - Biom...

      Biomass Boiler-Hot Sale- Easy Installation Low Heating Value Fuel Wood Rice Husk Pellets etc. Introduction : Biomass Steam Boiler is horizontal three-back water fire pipe composite boiler. Fix fire tube in drum and the light pipe water wall is fixed on the right and left sides of the furnace. With light chain grate stoker for mechanical feeding and by the draft fan and blower for mechanical ventilation, realize mechanical taphole by scraper slag remover. The hopper of fuel drops to ...

    • Rapid Delivery for Condensing Gas Boilers - LPG Pressure Tank – Double Rings

      Rapid Delivery for Condensing Gas Boilers - LP...

      Introduction: Pressure vessel equipment plays an important role in the petrochemical industry, the energy industry, scientific research and military sectors etc. Pressure vessel container body consist of cylinder, sealing head, flange, sealing elements, open pore and connected pipe, bearing. In addition, also equipped with safety devices, meter and safety internals for protection purpose . Pressure Vessel Main Performance Parameter List Steam Pressure1.0Mpa Inlet Temperature 250℃ S...

    • Wholesale Steam Boiler Installation - Installation & Technology Service – Double Rings

      Wholesale Steam Boiler Installation - Installa...

      Installation Procedure Step 1. Slag Extruder put into Foundation| Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair. Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue. Step 4. Connect Economizer ( Up Parts) and Gas Flue. Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak. Step 6. Lift Dust Cleaner to Foundation. Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer . Step 8. Lift I.D Fan to Foundation Step...