Installation Procedure
Step 1. Slag Extruder put into Foundation|
Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair.
Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue.
Step 4. Connect Economizer ( Up Parts) and Gas Flue.
Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak.
Step 6. Lift Dust Cleaner to Foundation.
Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer .
Step 8. Lift I.D Fan to Foundation
Step 9. Connect and fix the Gas Flue between Dust Cleaner and I.D Fan .
Step 10. Lift and Install Chimney , Connect I.D Fan with Chimney.
Step 11. Install F.D Fan
Step 12. Install Coal Feeder
Step 13. Install Reducer
Step 14. Install Valve&Gauge in Boiler Body
Install Valve&Gauge of Economizer
Step 15. Install Steam Distribution Cylinder,connect Main Steam Pipe and Valve&Gauge.
Customer arrange Steam Pipe Route according to the real situation in their factory.
Step 16. Install Water Pump and Valve&Gauge
Customer arrange Water Pipe Route according to the real situation in their factory.
Vertical Style Stainless Steel Water Pump need Vertically Installation.
Step 17. Install the Light,Motor Electric Wire and Electric Control Cabinet
Customer arrange Electric Wire Route according to the real situation in their factory.
Step 18. Install Water Treatment
All Boiler Installation Finish
Note: This Procedure was recommended by Double Rings. Real Operation is according to local situation and Manual. Photos in the paper is just to display.Real Equipments are subject to actual receipt cargo.
Service after Sale
Service after Sale: | |
Warrant Time | One Year for Whole Boiler without mistake operation after shipment. |
Technology Service | For life.Customer has any questions about the boiler, our engineers will serve and supply the Technology Service immediately. |
Guidance Installation | After finish the foundation and boiler arrived in the customer’s factory,two engineers will go to customer’s factory to guidance installation with local workers . |
Commissioning | After installed, the boiler will be commissioning and training for 2days. |
Charge | The buyer should provide air tickets with round trip, accommodation, food and local communication and transportation for the engineers, plus the subsidy for each engineer. |
Product detail pictures:
Related Product Guide:
Boiler Structure
We believe that long term partnership is a result of high quality, value added service, rich experience and personal contact for Chinese wholesale Industrial Steam Boilers - Installation & Technology Service – Double Rings , The product will supply to all over the world, such as: Honduras, Namibia, Czech Republic, We supply skilled service, prompt reply, timely delivery, excellent quality and best price to our customers. Satisfaction and good credit to every customer is our priority. We focus on every detail of order processing for customers till they have received safe and sound items with good logistics service and economical cost. Depending on this, our products and solutions are sold very well in the countries in Africa, the Mid-East and Southeast Asia. Adhering to the business philosophy of ??customer first, forge ahead', we sincerely welcome clients from at home and abroad to cooperate with us.
By Charlotte from Finland - 2017.12.09 14:01
The factory workers have a good team spirit, so we received high quality products fast, in addition, the price is also appropriate, this is a very good and reliable Chinese manufacturers.
By James Brown from Hongkong - 2018.05.15 10:52