The Boiler Room has already finished , and the Foundation has also been built. Then, 20T Thermal Oil Boiler Boiler Boy was Installed above the Fundation .
After the boiler body was in site, finish the Insulation meterial for the boiler body.
Then, begin to install the Multip Tube Dust Cleaner.
Install the Water Film Dust Cleaner .
Install the Pipes .
Install the Fuel Feeder.
Install the I.D Fan.
Check the Installation .
Post time: Jul-13-2021