We take "customer-friendly, quality-oriented, integrative, innovative" as objectives. "Truth and honesty" is our management ideal for pellet thermal oil boiler, fleck water treatment, Pressure Vessel, To supply prospects with superb equipment and providers, and constantly build new machine is our company's organization objectives. We look ahead for your cooperation.
Professional China Water Tube Boiler - Installation & Technology Service – Double Rings Detail:

Installation Procedure

Step 1. Slag Extruder put into Foundation|
Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair.
Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue.
Step 4. Connect Economizer ( Up Parts) and Gas Flue.
Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak.
Step 6. Lift Dust Cleaner to Foundation.
Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer .
Step 8. Lift I.D Fan to Foundation
Step 9. Connect and fix the Gas Flue between Dust Cleaner and I.D Fan .
Step 10. Lift and Install Chimney , Connect I.D Fan with Chimney.
Step 11. Install F.D Fan
Step 12. Install Coal Feeder
Step 13. Install Reducer
Step 14. Install Valve&Gauge in Boiler Body
Install Valve&Gauge of Economizer
Step 15. Install Steam Distribution Cylinder,connect Main Steam Pipe and Valve&Gauge.
Customer arrange Steam Pipe Route according to the real situation in their factory.
Step 16. Install Water Pump and Valve&Gauge
Customer arrange Water Pipe Route according to the real situation in their factory.
Vertical Style Stainless Steel Water Pump need Vertically Installation.
Step 17. Install the Light,Motor Electric Wire and Electric Control Cabinet
Customer arrange Electric Wire Route according to the real situation in their factory.
Step 18. Install Water Treatment
All Boiler Installation Finish
Steam Boiler Equipment Layout
Note: This Procedure was recommended by Double Rings. Real Operation is according to local situation and Manual.   Photos in the paper is just to display.Real Equipments are subject to actual receipt cargo.

Service after Sale

Service after Sale:
Warrant Time One Year for Whole Boiler without mistake operation after shipment.
Technology Service For life.Customer has any questions about the boiler, our engineers will serve and supply the Technology Service immediately.
Guidance Installation After finish the foundation and boiler arrived in the customer’s factory,two engineers will go to customer’s factory to guidance installation with local workers .
Commissioning After installed, the boiler will be commissioning and training for 2days.
Charge The buyer should provide air tickets with round trip, accommodation, food and local communication and transportation for the engineers, plus the subsidy  for each engineer.

 


Product detail pictures:

Professional China Water Tube Boiler - Installation & Technology Service – Double Rings detail pictures

Professional China Water Tube Boiler - Installation & Technology Service – Double Rings detail pictures


Related Product Guide:
Boiler Structure

We strive for excellence, services the customers", hopes to be the top cooperation team and dominator business for personnel, suppliers and prospects, realizes benefit share and continual promotion for Professional China Water Tube Boiler - Installation & Technology Service – Double Rings , The product will supply to all over the world, such as: Pakistan, Barbados, Detroit, We've got won a good reputation among overseas and domestic clients. Adhering to the management tenet of "credit oriented, customer first, high efficiency and mature services", we warmly welcome friends from all walks of life to cooperate with us.
  • High production efficiency and good product quality, fast delivery and completed after-sale protection, a right choice, a best choice.
    5 Stars By Nick from Hungary - 2017.09.28 18:29
    Product quality is good, quality assurance system is complete, every link can inquire and solve the problem timely!
    5 Stars By Yannick Vergoz from Zurich - 2017.12.31 14:53
    Write your message here and send it to us

    Related products

    • Factory Price For Biomass Fired Boiler - Pellets Shells Husk Biomass Boiler – Double Rings

      Factory Price For Biomass Fired Boiler - Pelle...

      Parameter : DZG(L)Horizontal Type Biomass-Burning Steam Boiler Main Technology Parameter List Model DZG2-1.0-S DZL2-1.25-S DZL2-1.57-S DZL2-2.45-S   DZG4-1.25-S DZL4-1.25-S DZL4-1.57-S DZL4-2.45-S DZL6-1.25-S DZL6-1.57-S DZL6-2.45-S  DZL8-1.25-S DZL8-1.57-S DZL8-2.45-S DZL10-1.25-S DZL10-1.57-S DZL10-2.45-S Rated Capacity T/h 2 4 6 8 10 Rated Working Pressure Mpa 1.0/1.25/1.57/2.45 1.25/1.57/2.45 1.25/1.57/2.45 1.25/1.57/2.45 1.25/1.57/2.45 Rated Steam Temp. ℃ 183/194/204/226 194/2...

    • Best-Selling Small Boiler - LPG Pressure Tank – Double Rings

      Best-Selling Small Boiler - LPG Pressure Tank ...

      Introduction: Pressure vessel equipment plays an important role in the petrochemical industry, the energy industry, scientific research and military sectors etc. Pressure vessel container body consist of cylinder, sealing head, flange, sealing elements, open pore and connected pipe, bearing. In addition, also equipped with safety devices, meter and safety internals for protection purpose . Pressure Vessel Main Performance Parameter List Steam Pressure1.0Mpa Inlet Temperature 250℃ S...

    • High Quality Electric Boiler - Biomass Wood Thermal Oil Boiler – Double Rings

      High Quality Electric Boiler - Biomass Wood Th...

      Thermal Oil Boiler used in Textile,Foods, Rubber ,Paper, Plastic, Wood, Building Materials etc. Feature: 1.Overall structure is reasonable and compact, easy to install. 2.Advanced design, Complete structure 3. Simple water cycle, reasonable structure of pressure parts, guarantee water quality, safe to run 4. Complete Ancillary equipment, advanced comprehensive technology

    • Top Quality Oil Central Heating - Vertical Gas Oil Boiler – Double Rings

      Top Quality Oil Central Heating - Vertical Gas...

      Introduction : 1. Compact structure, small installation area, easy to install. 2. Good heating surface , low exhaust gas temperature 3. The world famous original burner, automatic and high efficient combustion, high combustion efficiency 4. Microcomputer automatic controller, overpressure protection and ultra-low water level automatic protection and automatic feed water . 5. Super thickness insulating layer design, good insulation effect, boiler surface temperature low, low losing he...

    • Reasonable price Boiler Power Plant - Gas Steam Boiler – Double Rings

      Reasonable price Boiler Power Plant - Gas Stea...

      Introduction : WNS series steam boiler burning oil or gas is Horizontal internal combustion three backhaul fire tube boiler, adopts boiler furnace wet back structure, high temperature smoke, gas turn to scour the second and third backhaul smoke tube plate, then after the smoke chamber. discharged into the atmosphere through the chimney. There are the front and back Smokebox Cap in the boiler, easy to maintenance. Excellent burner adopts combustion automatic ratio adjustment , feedwater ...

    • OEM/ODM China New Boiler - Boiler Tube – Double Rings

      OEM/ODM China New Boiler - Boiler Tube –...

      More Photos Boiler Steel Pipe/Tube is a kind of seamless steel pipe. The manufacturing method is the same as seamless steel pipes, but there are strict requirements for the steel grades used to manufacture boiler steel pipes. According to the temperature level, it is divided into two types: low pressure boiler tube and high pressure boiler tube.